Authority to modify a construction contract comes from the contract, not from a job title or from who happens to be standing in front of you. Project managers, superintendents, architects, engineers, inspectors and owner representatives all give instructions daily. Only some of them can bind the contract, and the difference usually surfaces at invoicing.

Requesting is not authorising

On any active project you will hear some version of these:

  • "Go ahead and do it this way."
  • "We'll sort the paperwork out later."
  • "The PM already knows about it."
  • "We'll resolve this at the next meeting."

Each may reflect a genuine project need. None is necessarily a contractual authorisation to change scope. In many contracts the power to approve a change order is limited to named individuals or depends on the issue of a specific document. Performing extra work on the strength of an informal conversation is what creates the difficulty later, when payment is requested.

Who typically holds it

Depending on the project, authority may sit with the owner, the general contractor, the architect, or formally designated representatives. Some contracts require a specific instrument before work begins — a signed change order, a construction change directive, a field work authorisation, or an internal form. Others allow provisional authorisation followed by later formalisation.

Whichever model applies, the reference is the contract and the project procedures, not the urgency of the moment.

Confirm important instructions in writing, the same day

When a request arrives verbally, the practical response is to record it immediately — by email, letter, the project management platform, or whatever medium the contract accepts. The point is not bureaucracy. It is preserving a clear record of:

  • who requested the change
  • when the request was made
  • what work was requested
  • which impacts were already known at that moment

The earlier this is captured, the less room there is for divergent recollections later. A short confirmation email sent the same afternoon costs nothing and settles a question that can otherwise take months.

Authority exists inside your company too

External approval is only half of it. Subcontractors that manage change orders well define internally who is responsible for each step. Some concentrate it in the project manager; others split it between field, engineering, contracts and finance. Either works, as long as everyone knows who:

  • evaluates whether a situation is a change
  • issues notices
  • prepares proposals
  • reviews pricing
  • tracks approvals
  • controls billing

When those responsibilities are undefined, important tasks either get skipped or get done twice.

Never assume

One of the most common sources of contractual conflict is the assumption that a particular person had authority to approve additional work. When in doubt, check the contract or confirm formally before proceeding. The check takes minutes; the dispute it prevents can run for months.

If you have identified a change but not yet secured authorisation, the next step is usually the change order notice — and the mechanics of the change order itself are covered in what a change order is and what it must contain.