A useful change order example is one you can copy the structure of, not just look at. The sample below is a worked electrical example, built from a realistic scope: an unforeseen structural brace forced six receptacles to move, and it came to $3,800.60 with a three-day schedule impact. Every field is explained underneath.

Reading the example field by field

The header does the boring but essential work: it ties this document to a specific contract so nobody can argue later about which agreement it amends.

  • Change order number — CO-014. Sequential, per project. Gaps in the sequence are what auditors ask about.
  • Date — the date you issue it, which should be close to the date the work was directed, not the date you finally got around to invoicing.
  • Contract number — BCG-2026-118. This is the line that makes the change order an amendment rather than a loose invoice.

The description is where change orders are won or lost

Compare what the example says with what most change orders say.

WeakStrong (the example)
Extra electrical workPer J. Smith's field direction on 07/29/2026, relocated 6 receptacles and 2 data drops on the north wall of Suite 210
Not our faultto clear an unforeseen structural brace not shown on drawing E-2.1
(nothing)Original scope per contract section 16.4 remains unchanged elsewhere

Three things make the strong version work: a person's name and a date, a drawing reference that can be independently checked, and an explicit statement of what did not change. The last one prevents the change order from being read as a renegotiation of the whole contract.

The cost breakdown

The example splits five lines rather than quoting one number. Labor is separated by trade level, because a journeyman hour and an apprentice hour are not the same cost and a reviewer will check that. Material is quantified in the unit it is bought in — 140 feet of EMT, not "conduit".

  • Journeyman electrician, 18 hr @ $78 = $1,404
  • Apprentice, 12 hr @ $44 = $528
  • 3/4" EMT conduit and fittings, 140 ft @ $3.85 = $539
  • Receptacles, boxes, plates, 6 ea @ $42 = $252
  • Cat6 data drops relocated, 2 ea @ $165 = $330

Subtotal $3,053. Overhead and profit at 15% adds $457.95, tax at 8.25% adds $289.65, and the total is $3,800.60. Notice that overhead and profit sits on its own line at a stated percentage. Folding it into the unit prices — charging $90 for a $78 hour — is the single fastest way to make a reviewer distrust the whole document.

Schedule impact and evidence

The example claims three days. That number matters more than it looks: extra work that extends the job but declares zero days is how contractors lose delay claims months later. If the work genuinely has no schedule impact, write zero — but write it deliberately.

The notes line references photos DR-0729-01 through DR-0729-06 and a daily report dated 07/29/2026. This is the quiet part that decides disputes. The change order asserts a condition existed; the daily report and photos prove it did, on that date, before the work started.

What is missing from most examples online

  • A named person who directed the change — most templates leave a blank nobody fills
  • A reference to the specific drawing or spec section in dispute
  • Separate signature blocks for contractor, general contractor, and owner, since contracts often require more than one
  • An explicit schedule impact field, rather than assuming zero by omission
  • A statement that the rest of the original scope is unchanged

The pillar piece covers the mechanics in more depth: what a change order is and what it must contain.